  1. Question 101: A new agile project manager accepts an assignment to manage a well-established team. Many team members have worked together on this product for several years.…
  2. Question 102: An agile coach realizes that a team responsible for a major release is a few months behind schedule. The marketing department is unaware of this delay, and is…
  3. Question 103: During planning for the next iteration, an agile team identifies most of the story points that are expected to be delivered. How should an agile practitioner w…
  4. Question 104: The scrum master for a large project must provide an estimate of what can be delivered in six months. What should the scrum master do?
  5. Question 105: An agile practitioner wants to ensure that stakeholders have current information about a project's progress. What should the agile practitioner do?
  6. Question 106: A product owner, new to the role, is very enthusiastic about an agile project with an energetic team. What should be done first to ensure successful delivery o…
  7. Question 107: Prior to a retrospective, discussions among team members indicate conflict. An agile practitioner wants to ensure an open and safe environment during the retro…
  8. Question 108: The customer needs assistance in determining the efficiency of a set of process activities within the solution. What should the agile team do?
  9. Question 109: What should a team do when they complete all sprint goals earlier than expected?
  10. Question 110: During a project meeting, a team is faced with a difficult decision. After discussion and deliberation, the project leader makes the final decision and ends th…