Certification of Capability in Business Analysis (CCBA) — Question 426
A business analyst (BA) has completed an impact analysis of a proposed change, gained approval for the change, and has updated the requirements. The project sponsor wants to be updated with an overview of the results. How should the BA communicate the results?
Answer options
- A. Schedule a requirements workshop
- B. Present the requirements at a high-level
- C. Email the requirements package
- D. Create use case scenarios
Correct answer: C
Explanation
The correct answer is C because emailing the requirements package allows the project sponsor to review all the details at their convenience. Options A and B involve more interactive and time-consuming methods that may not be as efficient for a straightforward update. Option D, while useful, does not directly convey the updated requirements as effectively as the requirements package.