PMI Risk Management Professional (PMI-RMP) Free Practice Exam Questions

196 real PMI Risk Management Professional (PMI-RMP) exam questions with answers and AI explanations. PMI certification prep — page 6 of 20.

  1. Question 53: A project has a 60% chance of a US$100,000 profit and a 40% chance of a US$100,000 loss. What is the expected monetary value for this project?
  2. Question 54: A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified a…
  3. Question 55: A project manager is developing the risk register and works with the team to analyze risks and determine their probability and impact. There is valuable histor…
  4. Question 56: As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the p…
  5. Question 57: The project’s customer has stated the project must be completed by a date indicated as the P90 date established on the Monte Carlo analysis. What should the pr…
  6. Question 58: Stakeholder deliverable reviews will start soon and additional work is expected to resolve any issues or required adjustments. Budget overruns during execution…
  7. Question 59: A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. A…
  8. Question 60: After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in risk response plan to help mitigate…
  9. Question 61: The project sponsor asks the project manager about the accuracy of the project data. The project manager realizes that some risks have not been updated recentl…
  10. Question 62: Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted. W…