PMI Risk Management Professional (PMI-RMP) Free Practice Exam Questions

196 real PMI Risk Management Professional (PMI-RMP) exam questions with answers and AI explanations. PMI certification prep — page 1 of 20.

  1. Question 1: What is the purpose of mitigating negative risks as a part of the risk response process?
  2. Question 2: A risk on the risk register is triggered. This triggered risk costs US$200,000 to mitigate and will overwhelm the project, causing it to fail if not mitigated.…
  3. Question 3: The risk manager is about to go on medical leave, but before departing, conducts a risk response planning review meeting with stakeholders. A new risk manager…
  4. Question 4: A mobile operator wants to test a new network prototype before conducting full implementation on the entire network. What type of risk response strategy did th…
  5. Question 5: The team has just completed a risk response planning session and identified responses for all the high and medium priority risks. What should the team do with…
  6. Question 6: Which of the following represents the best description of the role of project manager for project risk management?
  7. Question 7: During what process should a project manager assign a risk owner?
  8. Question 8: PESTLE, TECOP, and SPECTRUM are three examples of prompt lists that can be used during risk management activities. Prompt lists are used to do which of the fol…
  9. Question 9: A project in the execution phase at the customer's site has an issue concerning new parts that do not fit properly into a machine. The site project manager can…
  10. Question 10: The project manager is unable to obtain a global consensus of competing subject matter experts and stakeholders on the project scope. This has caused a one- mo…